Full development cycle from origination to COD

Typical 18–36 months depending on scale, grid queue, and permitting — grid access governs.

ALLReviewed 01 Jun 2026Next review 01 Sept 2026
    Indicative phases:
  • Originate & assess: 4–8 weeks
  • Site & grid studies: 2–4 months
  • Offtake & PPA: 2–6 months (parallel)
  • Permitting & registration: 3–9 months
  • Build (EPC): 6–18 months by scale
  • Commission & operate: ongoing

Mining and utility-scale projects at the upper end. Honest caveat: grid connection approval is often the longest pole in the tent.

timelinedevelopmentcodgrid